The audit report must be submitted requesting design certification and/or performance certification within six (6) months of the declared end date of the Interim Measures.
A remote audit occurs if the site visit cannot be postponed due to significant impact of delaying the site visit on VVB and/or project developer due to timeline/commitment as per validation/verification or Gold Standard Verified Emission Reductions ...
The audit may include but not be limited to validation, verification, the inclusion of Voluntary Project Activities (VPAs), design change review, etc. It must be transparently disclosed in the audit report that the audit is undertaken remotely and ...
Unless already addressed satisfactorily as a part of the existing Environmental and Social Impact Assessment (ESIA) report, the opinion of an independent external expert(s) should be provided. Based on relevant CVs submitted by the Project ...
According to LUF Activity Requirements 2.1.17, the inclusion of new areas shall follow the Project Design Certification process as per Principles and Requirements. The Project Developer should assess if the new areas present material differences from ...