No. Project activities planning to make use
of waste materials that are already in use in the pre-project situation shall
NOT be eligible unless convincing evidence is provided to show that the current
users agree with the shift of use resulting from the project. In the absence of
such an agreement, the Project Developers shall demonstrate that the project activity makes use of surplus
waste materials and shall include this
analysis in the Monitoring Plan.